Engineering report says it would have cost $4.7 billion more to complete SC nuclear project, agency says | The State

Engineering report says it would have cost $4.7 billion more to complete SC nuclear project, agency says | The State:

That revised price tag was submitted to the Fairfield County project’s main contractor nine months before the partners in that effort — the Cayce-based SCANA utility and state-owned Santee Cooper utility — abandoned it.